ACTION: Define what
is needed on admin/organizing side for e.g. FSoC app to potentially
provide; make a wiki page that might be a future idea page.(quaid,
15:20:11)
Project naming to Fedora Marketing(quaid, 15:22:54)
Current name "Summer Coding" is
hemisphere-specific and coding-specific, where we want to be 2x/year
and ready for "any" contribution.(quaid,
15:24:52)
Fedora Marketing team requested to help with
new name brainstorming, no Trac ticket for this in Marketing queue
yet(quaid,
15:25:25)
ACTION: quaid to
email SIG about naming discussion in Marketing; will bring stuff
back to SIG along the way.(quaid,
15:27:44)
Project planning for next session(quaid, 15:28:45)
ACTION: quaid Make a
Sep-Feb planning wiki page(quaid,
15:29:14)
AGREED: 2x/year
application review cycle, with student project to start on schedule
agreed with mentor to allow for the varied schedules in the
world.(quaid,
15:47:01)
AGREED: review the
2x/year after first 12 months (or so) to see if there is value or a
way to increase(quaid,
15:47:35)
ACTION: get
algorhythm(s) out to the FSoC project so they are aware of the
planning here(quaid,
15:48:28)
IDEA: Session 1 review
period: 21 Feb to 07 Apr, Session 2 review period: 24 Oct to 07
Nov(quaid,
15:59:58)
IDEA: Give students
more time, including a soft and hard deadline(quaid,
16:00:19)
IDEA: "coding time is 4
months" and allow that start/end of 4 month to be within a 6+ month
time frame(quaid,
16:01:55)
IDEA: Session 1 review:
24 Mar to 07 Apr. Session 2 review: 24 Oct to 07 Nov [FIXED](quaid,
16:02:59)
AGREED: we have the
basic structure and agreement that a rolling program would work and
is desireable(quaid,
16:03:43)